    Home » Manpower shortage derails Zungeru power plant Dec 2019 deadline 

    Manpower shortage derails Zungeru power plant Dec 2019 deadline 

    September 6, 2017
    Share
    Facebook Twitter LinkedIn WhatsApp
    *Minister of Power, Works and Housing, Mr. Babatunde Fashola at the Zungeru hydro-power plant.

    Michael James
    06 September 2017, Sweetcrude, Lagos – The December 2019 deadline set for the completion of the 700-megawatts hydro-electric power plant in Zungeru, Niger State, is no longer feasible due to shortage of manpower.

    The was made known by the China National Electric Engineering Company Limited, CNEEC, handling the project.

    Deputy Project Manager, CNEEC-Sinohydro Consortium, Mr. Xiao Nie, said the first unit of the project, which is currently at 47 per cent completion, would be delivered in 2020 instead.

    “The project consists of a dam for storage reservoir for a maximum operation water level of 230 metres and total storage capacity of 11.4×109 meters.

    “The dam would be helpful for flood control, development of fisheries and agriculture. The navigable period and the length of the fairway will also be extended,” Nie stated.

    Meanwhile, about 3,000 Nigerians have been engaged, with majority of them coming from Zungeru, just as Nie noted that the consortium has assisted the host community in different ways, including skills acquisitions for youths.

    Related News

    AfDB to provide $184.1m for Africa’s largest solar energy and battery storage project

    Tinubu pardons Ken Saro-Wiwa, confers national honours on Ogoni Nine

    NCDMB Executive Secretary becomes member of APPO Board

    E-book
    Resilience Exhibition

    Latest News

    LASG approves seven dedicated truck parks for Lekki Port axis

    June 13, 2025

    NCDMB Executive Secretary joins AEW 2025 amid focus on enhancing local capacity

    June 13, 2025

    AfDB to provide $184.1m for Africa’s largest solar energy and battery storage project

    June 13, 2025

    NSC seeks closer collaboration with Police to boost port enforcement

    June 13, 2025

    Can the African Energy Bank transform the continent’s refining and downstream future?

    June 13, 2025
    Demo
    Facebook X (Twitter) Instagram
    • Opec Daily Basket
    • Oil
    • Power
    • Gas
    • Freight
    • Financing
    • Labour
    • Technology
    • Solid Mineral
    • Conferences/Seminars
    • Community Development
    • Nigerian Content Initiative
    • Niger-Delta Question
    • Insurance
    • Other News
    • Focus
    • Feedback
    • Hanging Out With Markson

    Subscribe for Updates

    Get the latest energy news from Sweetcrudereports.

    Please wait...
    Please enter all required fields Click to hide
    Correct invalid entries Click to hide
    © 2025 Sweetcrudereports.
    • About Us
    • Advertise with us
    • Privacy Policy

    Type above and press Enter to search. Press Esc to cancel.