Yenagoa — Shell has completed a scheduled maintenance at its 200,000 barrels-per-day Bonga deep water storage and offloading vessel in Nigeria, a spokesperson said.
The Shell Nigeria Exploration and Production Company said in a statement that the maintenance was completed in 22 days, less than the scheduled 30 days.
Bonga is typically one of the larger export streams from Nigeria.
“Commissioning and start-up activities are in progress and will culminate in ramp up of oil and gas production in the coming days,” the spokesperson said.
(Reporting by Tife Owolabi, writing by MacDonald Dzirutwe Editing by Shri Navaratnam) – Reuters