04 March 2017, News wires – Wood Group announced Thursday that it has completed a seven month front end engineering design (FEED) development for Noble Energy’s leviathan field development project in the Eastern Mediterranean Sea.
The company also revealed that it has started detailed engineering work for the platform, including the topsides and jacket. The FEED and detail design has a total contract value of approximately $95 million.
The estimated 30,000 ton fixed platform is being initially designed to process 1.2 billion cubic feet of gas per day, expandable to 2.1 Bcfpd to accommodate future production.
“Wood Group’s global engineering experience in delivering large-scale offshore gas production facilities and proven ability to deliver safe, cost-effective and efficient solutions will help Noble Energy and its partners meet the high standards, cost requirements and delivery schedule of the Leviathan field development,” Robin Watson, chief executive of Wood Group, said.
“We are proud to be a valued partner in this major project,” he added.
- Rigzone