    Home » 28 plants generate 5,329MW of electricity in March 2025

    28 plants generate 5,329MW of electricity in March 2025

    April 30, 2025
    Share
    Facebook Twitter LinkedIn WhatsApp
    *Egbin Power plant.

    Mkpoikana Udoma

    Port Harcourt — 28 grid-connected electricity generation plants across Nigeria generated an average of 5,329 megawatts, MW, of electricity in March 2025, reflecting a marginal decline of 2% from the 5,435MW recorded in February 2025.

    Data on the operational performance of power plants released by the Nigerian Electricity Regulatory Commission, NERC, highlighted that the 28 plants achieved only a 39% availability factor despite their cumulative installed capacity of 13,625MW.

    The report showed that larger power plants, including Egbin ST, Delta GS, Kainji, Shell’s Afam VI, Zungeru, Odukpani, Shiroro, Jebba, Okpai, Azura IPP, and Geregu, contributed 3,977MW on average—accounting for 74.6% of the total energy generated in December.

    Egbin ST and Kainji emerged as the highest producers, with average outputs of 642MW and 513MW respectively, while Delta followed with 494MW.

    Smaller power plants such as Afam I-V, Sapele ST, Olorunsogo NIPP, Omotosho NIPP, Sapele GT NIPP, Ihovbor NIPP, Geregu NIPP, Omotosho, Olorunsogo, Ibom Power, Rivers NIPP, Omoku, Trans Amadi, Paras, Taopex Energy, Mepp, and Dadin Kowa generated a combined average of 1,353MW, representing 25 4% of the total energy output.

    However, some plants performed below capacity. For instance, Trans Amadi and Dadin Kowa produced just 4MW and 16MW on average, while Olorunsogo and Alaoji NIPP failed to generate any power during the period, despite its installed capacity of 500MW.

    NERC’s data also revealed that the average hourly available capacity from the 28 power plants was 4,842MWh/h during the review period, further underscoring the gap between installed capacity and actual performance in Nigeria’s power sector.

    Related News

    US praises Nigeria’s CNG push, urges wider adoption

    IEA sees significant 2027 oil surplus after Hormuz recovery

    ‘Steel, power sectors must align to drive industrial growth’

    Comments are closed.

    E-book
    Resilience Exhibition

    Latest News

    US praises Nigeria’s CNG push, urges wider adoption

    June 19, 2026

    NEMSA unveils solar mini-grid rules, boosts renewable energy oversight

    June 19, 2026

    Again, Obi questions Nigeria’s rising debt, demands borrowing transparency

    June 19, 2026

    NMDPRA, NEITI deepen data transparency drive to strengthen reforms

    June 19, 2026

    Truckers build database amid management inefficiencies in Lagos ports

    June 19, 2026
    Demo
    Facebook X (Twitter) Instagram
    • Opec Daily Basket
    • Oil
    • Power
    • Gas
    • Freight
    • Financing
    • Labour
    • Technology
    • Solid Mineral
    • Conferences/Seminars
    • Community Development
    • Nigerian Content Initiative
    • Niger-Delta Question
    • Insurance
    • Other News
    • Focus
    • Feedback
    • Hanging Out With Markson

    Subscribe for Updates

    Get the latest energy news from Sweetcrudereports.

    Please wait...
    Please enter all required fields Click to hide
    Correct invalid entries Click to hide
    © 2026 Sweetcrudereports.
    • About Us
    • Advertise with us
    • Privacy Policy

    Type above and press Enter to search. Press Esc to cancel.