Oscarline Onwuemenyi
21 March 2017, Sweetcrude, Abuja – The Minister of Works, Power, and Housing, Mr. Babatunde Fashola, has said that work would begin this year on the 40 megawatts Kashimbila Hydro Power Plant in Taraba State.
Fashola said this while speaking with newsmen in Maiduguri after a tour of projects in the North East.
He said the government was equally making efforts to complete the Mambilla Power Station, also in Taraba.
“As for the Mambilla plant, the contractor is back to site after he was mobilised. But he has lots of challenges; he has to open a letter of credit and import equipment, among other things.
“For Kashimbilla project, we have made progress in terms of project planning. We are in the final stage of pricing and we expect that we will start work this year,” Fashola said.
According to him, preparatory work is going on and the ministry is considering the best route to move the equipment to the site.
“This is part of project planning that makes for efficient project execution,” the minister said.
Fashola said that estate valuers had been engaged to prepare ground for easy compensation of the natives.
“We already have estate valuers who are valuing the whole site where the plant will be constructed so that when compensation is paid, there will be no problem when work construction begins.
“Zungeru project had problems relating to compensation as no prior work was done like this one,” Fashola said.
He lauded the National Assembly for its planned amendment of the Public Procurement Act to provide for more mobilisation fee to contractors, especially those handling road projects.
“I want to acknowledge the tremendous support that our ministry is receiving from the National Assembly. Amending the Act will be useful now; if you get more money to contractors in an economy that is getting out of recession, it will help in reflating the economy,” the minister said.
Fashola added that injecting more money into the economy, through lawful means, would help in quick recovery from the current recession.
He assured that government would pay more attention to federal roads in all states of the North East within the shortest possible time.
“The most important thing is that we are back to site and very soon those nasty experience on our roads will be over. We have gathered momentum and our contractors are working while the journey is getting progressively better and ultimately it will return to what it used to be,” the minister said.